HomeCommunityPalo Corona restores historic flood plain below Rancho Cañada Golf Club

Palo Corona restores historic flood plain below Rancho Cañada Golf Club

Published November 4, 2026

By CHOICE MUIVAH

Since June 2025, the Rancho Cañada Floodplain Restoration Project has excavated 15 feet of sediment built up from the old Rancho Cañada Golf Club to connect the historic flood plain that once covered Carmel Valley to the Carmel River, replanting trees and local plants, reintroducing native species and expanding Palo Corona Regional Park.

Historically, the flood plain was shallow and wide and covered the Carmel Valley, but due to development, it eroded, becoming narrow and deep. The excavation for the area that covers the previous golf course will span 40 acres and about a mile of the Carmel River with roughly 80-90 acres of the surrounding grading being affected due to relocation of sediment to upland areas as well as around the park.

“That’s what this project is trying to do: provide that space for the water to flood out over the landscape,” says Jake Smith, planning and conservation program manager of the Rancho Cañada Project.

In order to restore the historic floodplain, about a football field’s footprint worth of sediment buildup was excavated. photo by CHOICE MUIVAH

As the project nears the end of phase two of three, with over 650,000 cubic yards of sediment removed, it will begin phase three to replant native plants and encourage the repopulation of species. The project will add a three-mile trail network that runs around the river corridor, connect to loop trails and go through a growing forest as a variety of about 10,000 native trees will be planted around the flood plain. A clear-span truss bridge will be built to span across the flood plain and will serve as another way for the public to experience the area and cross the preserve.

To ensure the reintroduction of local wildlife, about 4,000 pounds of native seeds will be spread and 175,000 plants will be planted to help create a thriving environment for the threatened California red-legged frog and western pond turtle as well as be a breeding ground for the endangered steelhead trout.

“We’re building the flood plain primarily for the benefit of the steelhead as well as all of the riparian and aquatic species that need this feature,” says Tim Frahm, the retired Central Coast steelhead project manager of 15 years who supported the technical review and acquisition planning of the Rancho Cañada Project in its early stages. 

Previously, the main Carmel River did not have deviations, but the Rancho Cañada Project plan will implement channels for the river to meander and spread into. photo by CHOICE MUIVAH

“We’re not just restoring the river, but we’re restoring a lot of the conditions or processes that healthy environments require,” says Smith.

Aside from improving conditions and reintroducing the native species, the flood plain will also help lessen the impact of flooding in areas such as the Hacienda Carmel Retirement Community.

“It’s also been designed to not only impact flood elevations, but actually improve conditions for folks that experience flooding upstream,” says Frahm.

With the help of Cutting Green Tape, a state program that aims to streamline the process of environmental restoration projects, the Rancho Cañada Project was able to raise $35 million to be fully funded by contributions from the National Fish and Wildlife Foundation, the Wildlife Conservation Board, the State Coastal Conservancy and the National Marine Fisheries Service.

The project completed phase one under budget and now nears its last stage, so the new addition to Palo Corona is expected to be completed and open to the public as early as March or as late as July 2027.